git-subtree-dir: bahn/wissensdatenbank git-subtree-split: 07a8196e5f9e55d027f90485beb95f4006387669
42 lines
1.6 KiB
Markdown
42 lines
1.6 KiB
Markdown
---
|
|
domain: "regulierung"
|
|
tool: "allgemein"
|
|
scope: "allgemein"
|
|
tags: ["domain:regulierung", "tool:allgemein", "scope:allgemein", "inb", "inb-2026", "regulierung", "recht"]
|
|
owners: []
|
|
contact: "einfachbahn@deutschebahn.com"
|
|
component_type: "pdf"
|
|
source: "www.dbinfrago.com"
|
|
source_version: ""
|
|
meta_fingerprint: ""
|
|
url: "https://www.dbinfrago.com/resource/blob/13131410/cafbb1c3c9cec2b63d2194225ea162c1/INB-2026-Hauptdokument-data.pdf"
|
|
part: "Frist für die Beauftragung"
|
|
kind: "chunk"
|
|
parent_url: "https://www.dbinfrago.com/resource/blob/13131410/cafbb1c3c9cec2b63d2194225ea162c1/INB-2026-Hauptdokument-data.pdf"
|
|
parent_hash: "f87111b87d53d1f1"
|
|
section: "Frist für die Beauftragung"
|
|
ziffer: ""
|
|
chunk_index: 379
|
|
chunk_fingerprint: "deab492aec4556f3"
|
|
last_updated: "2026-06-26"
|
|
review_status: "approved"
|
|
review_notes: ""
|
|
content_hash: "a76c25d1bc9bc940"
|
|
---
|
|
|
|
> Kontext: inb 2026 hauptdokument > Frist für die Beauftragung
|
|
|
|
## **Frist für die Beauftragung**
|
|
|
|
Der ZB muss eine Betriebsprogrammstudie für aT und Versuchsfahrten spätestens 6 Wochen vor dem Beginn des in der Beauftragung genannten Transportzeitraums nach Ziffer 5.4.9.3 bei der DB InfraGO AG beauftragen.
|
|
|
|
Der ZB darf
|
|
|
|
- die Betriebsprogrammstudie mit einem größeren Vorlauf und / oder
|
|
|
|
- mit einem längeren Transportzeitraum als dem in Ziffer 5.4.9.3 geregelten Mindestzeitraum
|
|
|
|
beauftragen. Hierbei sind durch den ZB die jeweiligen Gültigkeitszeiträume der Machbarkeitsstudien aT für die in der Studie zu betrachtenden Transporte zu beachten. Die Gültigkeitszeiträume müssen mindestens den kompletten Transportzeitraum abdecken.
|
|
|
|